After shot blasting, the substrate needs to be vacuumed.
|
 |
 |
| The floor is ready for the application of KÖSTER VAP 2000. |
The KÖSTER VAP 2000 vapor barrier is installed. |
 |
 |
The final floor: KÖSTER EM-VS coating is applied in two layers. (Custom Color RAL 7000) |
| Kohde | Codfish Facility in Oliveira do Hospital, Portugal | | Käyttöalueet | Lattian pinnoitus | | Kuvaus | The old epoxy flooring detached from the floor due to osmotic action. To achieve a strong bonding between the new coating and the old substrate, the floor was shotblasted and vacuumed. Then KÖSTER VAP 2000 was applied with approx. 0,5 kg/m²., then two layers of EM-VS in a custom color (RAL 7000) , with silica sand (0.3) between the layers. The final consumption was approx. 0,6 kg/m², The products cured for 4 days before re-installing the machinery and facility equipment. | | Käytetyt tuotteet | KÖSTER KB-Pox® EM-VS KÖSTER VAP® 2000 | | Urakoitsija | Magnus Salus |
|
|